Washrooms
Paediatrics ED
Client
MK NHS Trust
Brief
Transformation of A+E into Paeds ED
Value
£500,000.00
Duration
12 weeks
Start Date
Nov 2017
Works Incorporated:
- Strip out and reconfiguration of partitions, M+E and all finishes.
- Creation of additional WC facilities.
- Formation of 5no consulting rooms, accomodating half height wall cladding with corner protection, new IPS, corian worktops and sliding curtain rails.
- Full M+E re-instatement, including ventilation and plumbing works, access control, fire alarms, data, CCTV and bed head trunking installs incorporating nurse call and medical gases.
- Pre and Post-Triage waiting areas accentuated by inset leaf patters to the flooring, bespoke vinyl wall graphics, iPad stations and feature lighting.
- All new doorsets, fully impact plastic-clad doors and frames and a bespoke glazed sliding system to one of the consultation rooms.
- Bespoke, green coloured Trovex sheeting clad nurse stations with corian tops.