Washrooms
Washroom Refurbishment
Client
RPC
Brief
Washroom Refurbishment
Value
£40,000
Duration
4 Weeks
Start Date
September 2016
Works Incorporated:
- Removal and demolition of existing staff wash facility in dust sensitive environment.
- Erection of dust screens, utilised dust control mats upon exit/ entry.
- Installation of structural supports and infill to existing drainage channel.
- Extension of existing structure to create a new access corridor and enlarged wash facility.
- New partitions, suspended ceilings and LED lighting.
- Hygienic lllumitex decoration and the inclusion of a crisp corporate branded orange band to feature walls.
- Cap and cove vinyl floor.
- Solid compact grade laminate IPS with a stainless steel wash trough, sensor taps and Dyson airblade hand-driers, accompanied by drain-off drip trays.