Entertainment/Leisure

Trampoline Park

Client

Bounce

Brief

Construction of the UK's first Trampoline Park

Value

£490,000.00

Duration

16 weeks

Start Date

February 2014

  • Foam Pit
  • Trampoline
  • Dodgeball
  • Cross Section
  • Stairs/ Door
  • Floor Area
  • Entrance
  • Induction Room
  • Induction Ceiling
  • Indented Lockers

Works Incorporated:

  • Reconfigure existing factory/office unit.
  • Demolition of part of the existing office block.
  • Mezzanine extension, new partitions, suspended ceilings, lighting, internal door sets, floor finishes & decoration.
  • To provide office facilities, party rooms and a kitchen.
  • Refurbish WC’s including new IPS, vanity units, cubicles, sanitaryware, wall & floor finishes and lighting.
  • Erect all trampoline equipment including basketball hoops, a ball pit and dodgeball court.
  • Erect access mezzanine from lower level to trampoline height including floor finish, fire protection, DDA escape ramp and personnel lift.
  • Adapt/renew heating & lighting in activity area.
  • Total internal fit out of reception building & briefing room.
  • Construct DDA access to reception building.
  • Construct bin store, install cycle stands, construct new pedestrian access to new gate in rear wall.

 