Commercial
Office Refurbishment and Furniture Installation
Client
V Group International
Brief
Spruce-Up of 2no Existing Office Spaces
Value
£36,000
Duration
4 Weeks (2 phases of 2 weeks)
Start Date
May 2016
Works Incorporated:
- Removal of partitions to form a more contemporary, open plan layout - focusing on the introduction of light and space.
- Installation of 600x600 LED panels.
- 3 Compartment Trunking utilised to tidy up power/ data.
- Total redecoration.
- New Floor Finishes.
- Introduction of blinds.
- Complete transformation of the layout with new furniture throughout.